Danos, L.L.C. v. Transcontinental Gas Pipe Line Company, LLC

  1. September 16, 2021

    Gas Pipeline Co., Contractor Settle $15M Project Dispute

    A Williams Co. unit and Danos LLC on Thursday announced they'd reached an agreement to settle a dispute over delays and the subsequent termination of a $15 million contract to rebuild a Pennsylvania natural gas storage facility.

  2. March 17, 2021

    Inspector Not To Blame For $15M Pa. Pipeline Project Delays

    A Texas federal judge has dismissed all claims against a company hired by a Williams Co. unit to oversee work on a $15 million natural gas storage facility project, finding an inspector didn't wrongfully interfere with another company's contract by ensuring the job was done well. 

  3. March 15, 2021

    Williams Unit Can't Double Dip On Costs, Contractor Says

    A Williams Co. unit should not be able to pursue a contractor for $11.24 million in costs to complete reconstruction work on a Pennsylvania natural gas facility since Williams will already be able to recover the costs through Federal Energy Regulatory Commission proceedings, the contractor told a Texas federal court Monday.

  4. January 17, 2019

    Contractor Seeks $10M After Pa. Pipeline Project Goes Awry

    A Houston-based Williams Partners LP pipeline unit delayed the reconstruction of a Pennsylvania natural gas facility that exploded two years ago, then improperly fired the company hired to do the job, the contractor claimed in a federal lawsuit seeking more than $10 million.

Hello! I'm Law360's automated support bot.

How can I help you today?

For example, you can type:
  • I forgot my password
  • I took a free trial but didn't get a verification email
  • How do I sign up for a newsletter?
Ask a question!